Management wants to start right away, with no preparation. What do I show them?
Not a task list, but what happens if the project starts unprepared. Without an approved Project proposal (04) and a place in the portfolio you have no mandate to start 1.
The brief is where projects most often break: missing assumptions, goals not derived from benefits, too little push-back on unrealistic demands. If management insists, log it as a risk with an owner 2.